Abstract: with the rapid development of construction industry in our country, more and more residential area, residential construction quality relates to the vital interests of the people, especially in the construction of low voltage electrical installation quality of good or bad, will directly affect people's quality of life, so the long low voltage electrical installation period according to the building engineering, process, interference, more collaboration area wide, the characteristics of more heavy inspection, improve the quality of construction, to ensure that the installation work smoothly. This article first analyzes the characteristics of low voltage electrical installation construction, and then detailed construction engineering are discussed from six aspects of low voltage electrical installation construction technology key points, provide a reference for industry workers.
Keywords: low voltage electrical installation; Lightning protection; Pipe embedded; The power distribution cabinet; debugging
中圖分類號(hào):TU74文獻(xiàn)標(biāo)識(shí)碼:A文章編號(hào):2095-2104(2013)
建筑工程低壓電氣安裝施工的特點(diǎn)
(一)工期長(zhǎng),工序繁多,涉及面廣
首先要進(jìn)行接地網(wǎng)、預(yù)埋線管、管件、底盒等土建工作并對(duì)其進(jìn)行焊接,待土建工作完成后要進(jìn)行必要的安裝調(diào)試,一切施工工作就緒后要進(jìn)行時(shí)運(yùn)行并進(jìn)行總調(diào)試,最后交由相關(guān)部門進(jìn)行質(zhì)量檢驗(yàn)和竣工驗(yàn)收。這一過(guò)程耗費(fèi)較長(zhǎng)時(shí)間,涉及土建、安裝、質(zhì)檢等多個(gè)工序,錯(cuò)綜復(fù)雜。
(二)低壓電氣安裝施工干擾多,交叉作業(yè)面廣
通過(guò)上面的分析我們得知,在進(jìn)行電氣安裝過(guò)程中,需要較長(zhǎng)的施工工期,施工工序的種類多,施工涉及面大。這些特點(diǎn)使得電氣安裝時(shí)容易受到多種內(nèi)外因素的干擾。因此,需要加強(qiáng)對(duì)這些施工干擾類型和成因的研究,以更好的為電氣安裝創(chuàng)造一個(gè)安全穩(wěn)定的安裝環(huán)境。
(三)要重視檢查工作,降低影響安裝質(zhì)量的因素
在建筑工程低壓電氣安裝過(guò)程中,因?yàn)橐艿蕉喾N外界因素的干擾和影響,使得安裝工序存在一些難以預(yù)測(cè)的質(zhì)量隱患。所以,要加強(qiáng)對(duì)安裝施工的多次檢查,防患于未然,保證建筑工程低壓電氣安裝的質(zhì)量。
建筑工程低壓電氣安裝施工技術(shù)要點(diǎn)
(一)施工前的準(zhǔn)備
要想做好建筑低壓電氣安裝工程的整體工作,就需要將其準(zhǔn)備工作做好,其準(zhǔn)備工作包含管件的預(yù)埋工作。在安裝工程進(jìn)行實(shí)際施工的過(guò)程中,經(jīng)常有工作人員對(duì)圖紙的觀察出現(xiàn)錯(cuò)誤,這樣就可能使得施工工作人員不能夠正確的預(yù)埋相關(guān)的管件。甚至部分安裝施工工人,根本不按照正確圖紙上的要求對(duì)管件進(jìn)行預(yù)埋工作。如果在實(shí)際的安裝工作過(guò)程中,出現(xiàn)類似的問(wèn)題或者漏洞,不僅僅是對(duì)安裝工程的整體質(zhì)量會(huì)產(chǎn)生威脅,與此同時(shí)也可能發(fā)生安全隱患。所以安裝工程在現(xiàn)場(chǎng)工作時(shí),需要施工管理者對(duì)預(yù)埋工作與圖紙進(jìn)行一一比對(duì),只有確認(rèn)無(wú)誤之后,才可以進(jìn)行正式的施工工作。
(二)管件預(yù)埋施工要求
隱藏工程中焊接配件是安裝工程的重要組成部分。施工人員的經(jīng)驗(yàn)不一致,有的人查看圖紙不小心,出現(xiàn)錯(cuò)埋、漏埋或失敗埋管道配件,不符合生產(chǎn)圖紙和施工技術(shù)規(guī)范的要求。現(xiàn)場(chǎng)施工管理人員應(yīng)對(duì)預(yù)埋件鋪設(shè)的網(wǎng)站的規(guī)格、數(shù)量、圖紙、管道涂料、噴嘴加工以及焊接檢驗(yàn)等進(jìn)行詳細(xì)檢查,經(jīng)檢查合格后方可進(jìn)入下道工序,以滿足規(guī)范要求。
(三)低壓動(dòng)力配電柜安裝
低壓配電盤柜主要為低壓配電室及消防泵站、公用公程的MCC柜及變頻柜,為保證用電的安全可靠,必須保證盤柜一次及二次回路安裝、接線的施工質(zhì)量,確保其為各用電設(shè)備提供可靠的電源供電。
盤柜在搬運(yùn)和安裝過(guò)程中,應(yīng)采取防震、防潮、防止框架變形和漆面受損等安全措施,必要時(shí)可將裝置性設(shè)備和易損元件單獨(dú)包裝運(yùn)輸,對(duì)于較大的盤柜,從卸貨區(qū)運(yùn)至現(xiàn)場(chǎng)前應(yīng)首先應(yīng)對(duì)運(yùn)輸?shù)缆愤M(jìn)行檢查,以避開障礙物。在盤柜進(jìn)入配電室前,應(yīng)要考慮盤柜進(jìn)入的預(yù)留通道。
盤柜在安裝前,建筑的屋頂、樓板施工完畢,不得滲漏,室內(nèi)的地面工作應(yīng)已完成,無(wú)積水無(wú)雜物。門窗安裝完畢,有可能損壞已安裝的設(shè)備或設(shè)備安裝后不能再進(jìn)行的裝飾工作應(yīng)全部結(jié)束,空調(diào)或通風(fēng)設(shè)施的也應(yīng)安裝完成。
盤柜及盤柜內(nèi)設(shè)備與各構(gòu)件間連接應(yīng)牢固。盤柜單獨(dú)安裝時(shí)其垂直、水平度偏差以及盤柜面偏差和接縫的允許偏差應(yīng)符合下表中的規(guī)定:
表盤柜垂直、水平度偏差要求
4、端子箱安裝牢固,封閉良好,并能防潮、防塵,安裝的位置應(yīng)便于檢查。盤柜的接地應(yīng)牢固良好,裝有電器的可開啟的門,以裸銅線與接地的金屬構(gòu)架可靠地接地。端子排無(wú)損壞、固定牢固,絕緣良好,端子有序號(hào),端子排便于更換與且接線方便,離地的高度宜大于350mm。
5、導(dǎo)線與電氣元件間采用螺栓連接牢固可靠,每個(gè)接線端子的每側(cè)接線宜為1根,不得超過(guò)2根,引入盤柜的電纜排列整齊,編號(hào)清晰,避免交叉,并固定牢固,不得使所接的端子排受到機(jī)械應(yīng)力,鎧裝電纜在進(jìn)入盤柜后,應(yīng)將鋼帶切斷,切斷處的端部應(yīng)扎緊,并應(yīng)將鋼帶接地,盤柜內(nèi)的電纜芯線,應(yīng)按垂直或水平有規(guī)律地配置,不得任意歪斜交叉連接。備用芯長(zhǎng)度應(yīng)留有適當(dāng)?shù)挠嗔俊?/p>
(四)電力電纜施工
1、電力電纜的運(yùn)輸及保管
(1)電纜在運(yùn)輸過(guò)程中不應(yīng)使電纜及電纜盤受到損傷,嚴(yán)禁將電纜盤直接由車上推下,電纜盤不應(yīng)平放運(yùn)輸及貯存;運(yùn)輸及滾動(dòng)電纜盤前,必須保證電纜盤牢固,電纜繞緊、滾動(dòng)時(shí)必須順著電纜盤上的箭頭指示或電纜纏緊方向。
(2)電纜及其附件到達(dá)現(xiàn)場(chǎng)后,應(yīng)及時(shí)進(jìn)行檢查,產(chǎn)品的技術(shù)文件應(yīng)齊全,電纜型號(hào)、規(guī)格、長(zhǎng)度應(yīng)符合圖紙要求,附件應(yīng)齊全,電纜封端應(yīng)嚴(yán)密。
2、電纜敷設(shè)
(1)電纜敷設(shè)前應(yīng)檢查電纜型號(hào)、規(guī)格是否符合設(shè)計(jì)要求,電纜外觀應(yīng)無(wú)損傷,絕緣良好。
(2)電纜放線架應(yīng)放置穩(wěn)妥,鋼軸的強(qiáng)度和長(zhǎng)度應(yīng)與電纜盤重量和寬度相配合。敷設(shè)前應(yīng)按設(shè)計(jì)和實(shí)際路徑計(jì)算每根電纜長(zhǎng)度,合理安排每盤電纜, 減少電纜接頭。
(3)電纜各支持點(diǎn)的間距,對(duì)于工程中所采用的全塑型電纜其水平不應(yīng)大于400mm ,垂直不應(yīng)大于1000mm。電纜的最小彎曲半徑應(yīng)大于10D(D為電纜外徑)。
(4)電纜敷設(shè)時(shí),電纜應(yīng)從盤的上端引出,不應(yīng)使電纜在支架及地面上摩擦拖拉。電纜敷設(shè)應(yīng)排列整齊,不宜交叉并對(duì)其應(yīng)加以固定,并及時(shí)裝設(shè)標(biāo)志牌。在電纜終端頭、電纜接頭、拐彎等處均應(yīng)加裝標(biāo)志牌。標(biāo)志牌上應(yīng)注明線路編號(hào),當(dāng)無(wú)編號(hào)時(shí),應(yīng)寫明電纜型號(hào),規(guī)格及起始點(diǎn),標(biāo)志牌的字跡應(yīng)清晰不易脫落,其掛裝應(yīng)牢固。垂直敷設(shè)或超過(guò)45度傾斜敷設(shè)的電纜在每個(gè)支架上應(yīng)固定,水平敷設(shè)的電纜在電纜首未端及轉(zhuǎn)彎處應(yīng)固定。
(5)外線電纜采用多列橋架敷設(shè),電纜的排列應(yīng)符合下面的要求:電力電纜和控制電纜盡量不配置在同一列橋架內(nèi),高低壓電纜,強(qiáng)電、弱電控制電纜應(yīng)按順序分層配置。并列敷設(shè)的電力電纜其相互的凈距應(yīng)符合設(shè)計(jì)要求。
(五)避雷安裝施工技術(shù)
接地裝置的位置必須是在地面之上,并根據(jù)設(shè)置的測(cè)試點(diǎn)的施工圖紙,接地電阻值必須符合設(shè)計(jì)要求。防雷接地鋪設(shè)的主干,在主干鋪設(shè)過(guò)程中,其埋藏的位置必須在批準(zhǔn)的行人通道埋深不小于 1m,當(dāng)鋪設(shè)均衡后,接地模塊應(yīng)保持與地面垂直或水平,如中國(guó)聯(lián)通與原土壤。接地模塊應(yīng)著眼于領(lǐng)先,引出線大于二。
引下線當(dāng)采取隱蔽操作,應(yīng)在抹灰層表面裝置引下線,不能彎曲要盡可能平坦,與支架焊接防腐漆。額外兩個(gè)接地連接線的配電室。可以將接地線的金屬部件和金屬管用于接地線與接地線之間的一個(gè)跳線。應(yīng)加在外殼接地線穿過(guò)墻壁,地板和地板鋼套管與地面聯(lián)通。當(dāng)電纜通過(guò)電流互感器,電纜頭的接地線通過(guò)零序電流互感器時(shí),電纜頭和響應(yīng)電纜金屬護(hù)套和接地導(dǎo)線的絕緣層的長(zhǎng)度為到地通過(guò)。
(六)低壓電氣的調(diào)試、運(yùn)行要求
當(dāng)整個(gè)低壓電氣安裝完成后,它的電氣工程評(píng)估的各個(gè)組成部分的操作實(shí)施是必要的,這樣才能保證低壓電氣設(shè)備和布線擊敗根據(jù)安裝的有效性。
配電設(shè)備的工作電壓、電流在正常狀態(tài)下,必須確保各檢測(cè)設(shè)備的質(zhì)量。試運(yùn)行電機(jī)在 2h 內(nèi),觀察電機(jī)助力轉(zhuǎn)向和機(jī)械轉(zhuǎn)動(dòng)后的候選人是正常的。交流電機(jī)啟動(dòng)在無(wú)負(fù)載條件下的兩個(gè)關(guān)斷時(shí)間保持 5min 以上,以確保電機(jī)冷溫度是正常的再次啟動(dòng)。無(wú)負(fù)載操作應(yīng)記錄數(shù)據(jù),如電流,電壓,溫度,運(yùn)行時(shí)間,確保電氣工程的要求得到滿足。確定電致動(dòng)器和指令的移動(dòng)設(shè)備分配的移動(dòng)方向,供電照明系統(tǒng)燈具回路控制和配電箱、照明控制序列的電路開關(guān)應(yīng)相互對(duì)應(yīng)。公共建筑照明系統(tǒng)通電調(diào)試時(shí)間,在 24 個(gè)住宅照明系統(tǒng)開機(jī)時(shí)間為 8h,燈始終保持運(yùn)行,運(yùn)行記錄每 2h 記錄一次。調(diào)試后保持 24 小時(shí)的電力,觀察檢查無(wú)異常。
結(jié)語(yǔ)
綜上,壓電器施工已成為電氣安裝的主要方式和環(huán)節(jié)。隨著人們對(duì)電氣安裝需求的增加,電氣施工中質(zhì)量的控制也在日益的提高和變化。在進(jìn)行低壓電氣施工的過(guò)程中,施工操作人員需要遵循規(guī)范的施工方法,做好相互工種間的協(xié)調(diào)工作,認(rèn)真研究低壓電氣安裝的特點(diǎn),做好核心配電技術(shù)的研究和掌握,嚴(yán)格將施工工藝相結(jié)合的建設(shè)和分配技術(shù)進(jìn)行良好的密切合作,以確保在施工過(guò)程中的施工質(zhì)量和安全。只有這樣,才能使建設(shè)項(xiàng)目在中國(guó)低壓電器的安裝和施工質(zhì)量到一個(gè)新的水平。
參考文獻(xiàn)
[1]金榮.建筑工程中低壓電氣安裝施工探究[J].現(xiàn)代商貿(mào)工業(yè),2010.1.
關(guān)鍵詞:低壓電網(wǎng) 設(shè)計(jì) 施工
引言
低壓電網(wǎng)是堅(jiān)強(qiáng)智能電網(wǎng)的重要組成部分,是直接連接廣大電力客戶的社會(huì)公共服務(wù)平臺(tái),是促進(jìn)經(jīng)濟(jì)社會(huì)發(fā)展、保障和服務(wù)民生的重要基礎(chǔ)設(shè)施。根據(jù)國(guó)家電網(wǎng)對(duì)低壓電網(wǎng)標(biāo)準(zhǔn)化建設(shè)的要求,結(jié)合本地區(qū)對(duì)低壓電網(wǎng)建設(shè)的經(jīng)驗(yàn),下面筆者將對(duì)低壓電網(wǎng)電力設(shè)計(jì)及施工中會(huì)遇到的部分重要問(wèn)題進(jìn)行探討,并針對(duì)設(shè)計(jì)與施工方案提出些許建議。
一、低壓電網(wǎng)的現(xiàn)狀
低壓電網(wǎng)的主要作用是分配和輸送電能,即通過(guò)低壓電網(wǎng)將電能輸送給廣大的電力用戶,因此低壓電網(wǎng)的可靠性就成為了供電企業(yè)和用戶所關(guān)注的焦點(diǎn)問(wèn)題。低壓電網(wǎng)的可靠性主要體現(xiàn)在電網(wǎng)的建設(shè)、改造、運(yùn)行維護(hù)以及管理等各個(gè)方面,其可靠性來(lái)衡量供電企業(yè)對(duì)用戶供電的能力,同時(shí)也是供電企業(yè)進(jìn)行可靠性管理的一項(xiàng)重要指標(biāo),以下就對(duì)低壓電網(wǎng)的現(xiàn)狀進(jìn)行簡(jiǎn)要分析:
(一)低壓電網(wǎng)設(shè)計(jì)不合理
由于在低壓電網(wǎng)電力建設(shè)的過(guò)程中,往往受當(dāng)?shù)赜秒娯?fù)荷、地形結(jié)構(gòu)、氣象條件等相關(guān)條件的影響,如果沒(méi)有進(jìn)行認(rèn)真、科學(xué)、合理的分析,使得低壓電網(wǎng)的設(shè)計(jì)與實(shí)際使用存在較大的偏差。近年來(lái)人民的生活水平不斷提高,使低壓電網(wǎng)不堪重負(fù),經(jīng)常發(fā)生線路導(dǎo)線、接戶線燒斷等現(xiàn)象;特別是城鄉(xiāng)規(guī)劃和道路等公用設(shè)施建設(shè)的不配套,造成低壓電網(wǎng)拆、改建的現(xiàn)象,而且低壓電網(wǎng)交跨的障礙物種類繁多,這些交跨點(diǎn)常常因垂直、水平的安全距離不足,給電網(wǎng)帶來(lái)很大的安全隱患。以及設(shè)計(jì)過(guò)程中對(duì)最大風(fēng)速、覆冰條件等估計(jì)不足,而引起機(jī)械強(qiáng)度不足而造成的倒桿事故。
(二)低壓電網(wǎng)的可靠性差
(1)一些早期的低壓電網(wǎng)建設(shè),由于技術(shù)水平、建設(shè)資金、配變?cè)O(shè)置等客觀因素的影響,低壓電網(wǎng)多采用多分支輻射式單向供電的方式。這種方式負(fù)荷分散性大、密度小、晝夜峰谷差大、用電設(shè)備配套也差。不少線路延伸過(guò)長(zhǎng),出現(xiàn)不必要的迂回線路和“卡脖子”現(xiàn)象,在高峰時(shí),末端用戶電壓往往偏低10%~15%甚至更低,從而降低了配電網(wǎng)絡(luò)的可靠性。
(2) 低壓電網(wǎng)的缺陷造成的事故,線路材料質(zhì)量把關(guān)不嚴(yán),如:電桿存在偏心,有露筋、跑漿、縱、橫向裂縫等現(xiàn)象,絕緣子瓷鐵結(jié)合不牢固、瓷件破損以及斷路器等各類設(shè)備的產(chǎn)品質(zhì)量低劣造成的隱患。線路施工不規(guī)范,在基礎(chǔ)施工時(shí)電桿埋深不足、基礎(chǔ)工程施工保養(yǎng)不當(dāng)、拉線安裝不規(guī)范、導(dǎo)線弧垂過(guò)大、過(guò)小、導(dǎo)線綁扎及連接不規(guī)范而造成的倒桿、短路、斷線、導(dǎo)線連接點(diǎn)燒毀等現(xiàn)象。
(3)外力破壞造成的各類事故,近年來(lái),浙江省臺(tái)州市因盜竊造成的電力設(shè)施破壞案件逐年增多,其中低壓電網(wǎng)設(shè)施被盜突出,電力設(shè)施盜竊現(xiàn)象已從個(gè)人作案發(fā)展到團(tuán)伙作案,甚至形成了偷竊、窩贓、運(yùn)輸、銷贓一條龍。去年以來(lái)臺(tái)州電網(wǎng)共發(fā)生偷盜破壞電力設(shè)施案件多起,由此帶來(lái)的直接、間接經(jīng)濟(jì)損失不計(jì)其數(shù);以及城市建設(shè)及相關(guān)基礎(chǔ)設(shè)施施工過(guò)程中的疏漏、道路交通肇事、違章建筑等,造成的外力破壞電網(wǎng)停電事故不斷發(fā)生。
二、低壓電網(wǎng)的設(shè)計(jì)
低壓電網(wǎng)往往受當(dāng)?shù)貧夂颉⒌匦?、用電?fù)荷等條件的影響,規(guī)劃設(shè)計(jì)的合理與否,直接影響人們的日常生活和電網(wǎng)安全運(yùn)行、維護(hù),這就要求勘測(cè)設(shè)計(jì)人員要全方位、多領(lǐng)域、廣角度的進(jìn)行規(guī)劃設(shè)計(jì);配電站選擇要根據(jù)實(shí)際情況,在安全可靠、投資合理 、標(biāo)準(zhǔn)統(tǒng)一、運(yùn)行高效的設(shè)計(jì)原則下,將標(biāo)準(zhǔn)化設(shè)計(jì)中的模塊合理的組合應(yīng)用,形成符合實(shí)際要求的10kV標(biāo)準(zhǔn)化配電站。
低壓電網(wǎng)的勘測(cè)定位(包括電桿、架線及電纜敷設(shè)、接戶線及配變安裝等),是決定低壓電網(wǎng)布局設(shè)計(jì)是否合理的重要一環(huán)。低壓電網(wǎng)的布局應(yīng)與各地配網(wǎng)規(guī)劃、城鎮(zhèn)、鄉(xiāng)村建設(shè)規(guī)劃及發(fā)展計(jì)劃相配合,所以,無(wú)論新建工程還是改造工程,在勘測(cè)定位時(shí),一定要遵循以配電變壓器為中心,三點(diǎn)一線、忌低好高、重前輕后、側(cè)深拒淺的原則進(jìn)行,A、B、C類供電區(qū)低壓供電半徑不宜超過(guò)150m;D類供電區(qū)低壓供電半徑不超過(guò)250m;E類供電區(qū)低壓供電半徑不超過(guò)400m。根據(jù)本地用電負(fù)荷的發(fā)展情況,(可考慮5~10年負(fù)荷增長(zhǎng)情況),正確預(yù)測(cè)和估算未來(lái)負(fù)荷發(fā)展空間;并做到路徑短,轉(zhuǎn)角少,少占農(nóng)田,不防礙公共安全,施工和運(yùn)行維護(hù)方便;總之,低壓配電網(wǎng)應(yīng)結(jié)構(gòu)簡(jiǎn)單、安全可靠。
三、提高供電可靠性
在低壓電網(wǎng)新建或改造時(shí),遵循“統(tǒng)一規(guī)劃、分步實(shí)施、因地制宜、適度超前”的原則,充分考慮不同地區(qū)在電源分布、負(fù)荷分布、負(fù)荷特性和供電可靠性要求等方面的要求,建設(shè)成臺(tái)區(qū)布局合理、線路架設(shè)規(guī)范、計(jì)量安裝標(biāo)準(zhǔn)、電能質(zhì)量?jī)?yōu)良的低壓電網(wǎng)。配電變壓器臺(tái)區(qū)必須依據(jù)“小容量、密布點(diǎn)、短半徑”的原則,合理選擇配電變壓器的位置;低壓配電網(wǎng)應(yīng)實(shí)行分區(qū)供電的原則,在規(guī)劃線路出線時(shí),一般可考慮至少2條低壓線路出線回路,低壓線路一般采用樹枝放射式結(jié)構(gòu),避免線路迂回現(xiàn)象;應(yīng)推廣集束化、電纜化線路和導(dǎo)線的絕緣化,提高供電可靠性。
供電企業(yè)應(yīng)定期巡視檢查低壓線路的桿塔基礎(chǔ)、拉線基礎(chǔ)和違章建筑物,對(duì)掏空的桿塔基礎(chǔ)、拉線基礎(chǔ)進(jìn)行及時(shí)維修,對(duì)造成低壓電網(wǎng)維護(hù)管理不到位的進(jìn)行責(zé)任制考核,加強(qiáng)對(duì)中小學(xué)生的宣傳教育,在線路通道等設(shè)置醒目的安全警示標(biāo)識(shí),對(duì)破壞、盜竊電力設(shè)施的犯罪分子進(jìn)行嚴(yán)厲的打擊;加強(qiáng)新聞宣傳力度。讓全社會(huì)都來(lái)關(guān)心、保護(hù)電力設(shè)施,減少外界因素產(chǎn)生的故障對(duì)可靠性造成的影響。
四、低壓電網(wǎng)的施工管理
低壓電網(wǎng)的施工管理就是建設(shè)單位進(jìn)行工程準(zhǔn)備、組織施工到竣工驗(yàn)收全過(guò)程所實(shí)施的各項(xiàng)管理工作的總稱,低壓電網(wǎng)施工管理在整個(gè)施工管理中具有關(guān)鍵性因素,要完善施工管理體系,保證施工的質(zhì)量和進(jìn)度,制定出切合實(shí)際和合理的施工方案,保證施工的標(biāo)準(zhǔn)化和規(guī)范化;建立起責(zé)任人追究制度,保證整個(gè)低壓電網(wǎng)建設(shè)工程能夠順利完成。
施工技術(shù)管理分為三個(gè)階段:
1、 施工材料管理:
按照工程施工的相關(guān)技術(shù)規(guī)程、工藝標(biāo)準(zhǔn)和有關(guān)管理規(guī)定等,做好施工當(dāng)天的材料、工具使用記錄,在整個(gè)工程改造中收集各種材料、工具的出廠合格證、生產(chǎn)許可證、試驗(yàn)報(bào)告等,應(yīng)做好對(duì)工程材料的外表檢查和各種工程材料的質(zhì)量證明書。比如對(duì)一些材料的常規(guī)檢查方法:鋼筋混凝土電桿:表面光潔平整,壁厚均勻,無(wú)偏心,露筋、跑漿、蜂窩等現(xiàn)象;低壓架空絕緣線:導(dǎo)體緊壓,無(wú)腐蝕,絕緣線端部應(yīng)有密封措施,絕緣層緊密擠包,表面平整圓滑,色澤均勻,無(wú)尖角、顆粒,無(wú)燒焦痕跡;金具:表面光潔,無(wú)裂紋、毛刺、飛邊、砂眼、氣泡等缺陷。
2、 施工技術(shù)管理
施工是一個(gè)積累、提高的過(guò)程,應(yīng)當(dāng)認(rèn)真作好各項(xiàng)工作的原始數(shù)據(jù)搜集、記錄、積累。并拍攝各個(gè)施工階段的影像資料,包括基礎(chǔ)施工階段、立桿架線階段、竣工驗(yàn)收階段等。相關(guān)管理人員要對(duì)工程施工交底,相關(guān)技術(shù)人員應(yīng)根據(jù)施工圖、施工工藝及施工措施向各級(jí)施工人員進(jìn)行認(rèn)真詳細(xì)的技術(shù)交底,未經(jīng)交底不得施工。各級(jí)技術(shù)人員應(yīng)經(jīng)常深入現(xiàn)場(chǎng)講解施工中存在的技術(shù)關(guān)鍵問(wèn)題,并要求持證上崗。
工程基礎(chǔ)施工前必須進(jìn)行復(fù)測(cè),當(dāng)與設(shè)計(jì)有較大誤差或開挖后地質(zhì)與設(shè)計(jì)不符時(shí),應(yīng)及時(shí)聯(lián)系相關(guān)部門?;A(chǔ)施工時(shí)應(yīng)按現(xiàn)行《電氣裝置安裝工程、35KV以下架空電力線路施工及驗(yàn)收規(guī)范》GB50173-92執(zhí)行;基礎(chǔ)回填土必須嚴(yán)格按施工規(guī)范要求進(jìn)行分層夯實(shí),只有在砼基礎(chǔ)周圍覆土夯實(shí)后,才能立桿;電桿埋深除圖紙注明外,嚴(yán)格按規(guī)程要求施工。如在基坑開挖過(guò)程中不能按設(shè)計(jì)要求施工或地形復(fù)雜地段,施工單位應(yīng)及時(shí)通知設(shè)計(jì)人員到場(chǎng)。新建變壓器房要與村部取得聯(lián)系和協(xié)商。
桿塔組立施工時(shí)應(yīng)按現(xiàn)行《電氣裝置安裝工程、35KV以下架空電力線路施工及驗(yàn)收規(guī)范》GB50173-92執(zhí)行;緊線前,確保耐張桿按設(shè)計(jì)要求向外角傾斜;安裝附件時(shí),如遇附件安裝不到位時(shí),必須嚴(yán)格有關(guān)技術(shù)標(biāo)準(zhǔn)執(zhí)行;安裝前應(yīng)檢查各類金屬件鍍鋅層是否完整無(wú)損,如有大面積剝落時(shí)應(yīng)聯(lián)系相關(guān)部門檢查是否合格,再行安裝;電桿傾斜度附合規(guī)程要求。
架線時(shí)嚴(yán)格按導(dǎo)線弧垂表來(lái)緊線。展放導(dǎo)線時(shí),應(yīng)采取保護(hù)導(dǎo)線措施(或采用小張力放線)以減少導(dǎo)線的磨損;架線前應(yīng)檢查絕緣子及金具鍍鋅層等是否完好;緊線時(shí),應(yīng)嚴(yán)格控制過(guò)牽引,緊線時(shí)應(yīng)考慮導(dǎo)線初伸長(zhǎng)對(duì)弧垂的影響,可采用減小弧垂的方法,弧垂減小一般按鋁絞線為20%,鋼芯鋁絞線為12%掌握。架線后弧垂確保符合規(guī)程要求。
電纜的埋設(shè)深度,電纜與各種設(shè)施接近及交叉的距離,電纜之間的距離和電纜明裝時(shí)的支持間距離應(yīng)符合相關(guān)規(guī)定;敷設(shè)電纜時(shí)彎曲半徑不應(yīng)小于:聚氯乙烯護(hù)套多芯電力電纜為10倍;交聯(lián)聚乙烯護(hù)套多芯電力電纜為15倍。鎧裝的電力電纜,彎曲半徑均不得小于電纜外徑的10倍(無(wú)鎧裝時(shí)為6倍);電纜與管道、道路、建筑物之間平行和交叉時(shí)的最小凈距 必須符合要求。所有電纜走向按出線倉(cāng)位順序排列,電纜相互之間保持一定間距,不重疊,盡可能少交叉,需交叉時(shí)在交叉處用防火隔板隔開。電纜夾層無(wú)積水,無(wú)雜物,通風(fēng)、照明、防小動(dòng)物措施等符合要求。
配電室和箱式變電站運(yùn)行狀況(包括箱體、開關(guān)、熔斷器、變壓器、互感器、防雷和接地、母線、電纜、無(wú)功補(bǔ)償裝置、指示儀表、照明、直流電源等)符合運(yùn)行標(biāo)準(zhǔn)規(guī)定。接地體規(guī)格、埋設(shè)深度應(yīng)符合設(shè)計(jì)規(guī)定,接地裝置的連接應(yīng)可靠。接地電阻值,應(yīng)符合有關(guān)規(guī)定 (100KVA及以上配變應(yīng)小于4歐姆、100KVA以下配變應(yīng)小于10歐姆、其他的各類設(shè)備等應(yīng)符合有關(guān)規(guī)定)。
施工質(zhì)量管理
施工單位應(yīng)必須堅(jiān)決貫徹執(zhí)行上級(jí)頒布的各種質(zhì)量管理文件、規(guī)程、規(guī)范和標(biāo)準(zhǔn),牢固樹立“質(zhì)量第一”的思想, 編制符合工程管理實(shí)際情況的質(zhì)量實(shí)施細(xì)則和措施,工程監(jiān)理、施工管理單位在工程實(shí)施過(guò)程中嚴(yán)格質(zhì)量控制和管理工作,定期檢查工程施工質(zhì)量情況。
施工單位應(yīng)編制訂質(zhì)量控制點(diǎn)、設(shè)置質(zhì)量控制卡、落實(shí)質(zhì)量控制,應(yīng)將作業(yè)指導(dǎo)書帶至現(xiàn)場(chǎng),嚴(yán)格按作業(yè)指導(dǎo)書程序、項(xiàng)目、質(zhì)量標(biāo)準(zhǔn)進(jìn)行施工作業(yè),保證每道工序和施工質(zhì)量符合驗(yàn)收標(biāo)準(zhǔn)。堅(jiān)持做到每分項(xiàng)、分部工程施工自檢自查,把好質(zhì)量關(guān),不符合要求的不處理好決不進(jìn)行下道工序施工。
施工單位必須有專人負(fù)責(zé)施工質(zhì)量檢測(cè)和核驗(yàn)記錄,并認(rèn)真做好施工記錄和隱蔽工程驗(yàn)收簽證記錄,整理完善各項(xiàng)技術(shù)資料, 建立建全工程技術(shù)資料檔案制度,按照有關(guān)要求或檔案資料管理辦法,收集、審查、整理施工記錄表格、試驗(yàn)報(bào)告等資料。確保施工質(zhì)量符合技術(shù)規(guī)范要求。
工程監(jiān)理、施工管理單位應(yīng)組織進(jìn)行隱蔽工程和關(guān)鍵工序檢查,對(duì)不合格的項(xiàng)目應(yīng)責(zé)成返工,督促施工單位做好質(zhì)量自檢,對(duì)違反工程質(zhì)量管理制度的人,將按不同程度給予批評(píng)處理和罰款教育,并追究其責(zé)任。對(duì)發(fā)生事故的當(dāng)事人和責(zé)任人,將按上級(jí)有關(guān)規(guī)定程序追究其責(zé)任并做出處理。
結(jié)束語(yǔ)
綜上所述,隨著城市建設(shè)的不斷發(fā)展,國(guó)家電網(wǎng)建設(shè)的迅猛發(fā)展,使得對(duì)低壓電網(wǎng)電力設(shè)計(jì)及施工的質(zhì)量要求越來(lái)越高。為了減少電網(wǎng)的故障發(fā)生頻率,提升電網(wǎng)運(yùn)行的安全性以及穩(wěn)定性,供電企業(yè)以及管理人員要認(rèn)真學(xué)習(xí)和掌握低壓電網(wǎng)電力設(shè)計(jì)及施工的一些基本要求和設(shè)計(jì)原則,在實(shí)際工作中推廣和應(yīng)用低壓電網(wǎng)設(shè)計(jì)及施工的最新方法,而促進(jìn)我國(guó)電力的發(fā)展。
參考文獻(xiàn):
《架空配電線路設(shè)計(jì)技術(shù)規(guī)程》
關(guān)鍵詞:地鐵低壓;電氣施工管線;預(yù)埋轉(zhuǎn)彎半徑
中圖分類號(hào):TM64 文獻(xiàn)標(biāo)識(shí)碼:A
目前,隨著經(jīng)濟(jì)發(fā)展和城市規(guī)模的擴(kuò)大,國(guó)內(nèi)建設(shè)地鐵的城市逐漸增多,低壓電氣在地鐵中作用也越來(lái)越重要。地鐵低壓電氣系統(tǒng)包括從降壓變電所配電變壓器低壓側(cè)AC0.4kV開關(guān)柜進(jìn)線開關(guān)上端到設(shè)備配電箱、燈具為止之間的配電設(shè)備和線路。地鐵低壓電氣設(shè)備主要包括AC0.4kV開關(guān)柜、有源濾波裝置、通風(fēng)空調(diào)電控柜、動(dòng)力照明配電箱(含智能照明系統(tǒng))、應(yīng)急電源裝置(EPS)等。本文結(jié)合地鐵低壓電氣施工的特點(diǎn),具體分析了其需要注意的幾個(gè)問(wèn)題。
一、土建及設(shè)備房裝修影響
土建基礎(chǔ)需要滿足設(shè)備尺寸和重量的要求,每個(gè)設(shè)備供貨商的開關(guān)柜尺寸和重量不一,且設(shè)備招標(biāo)時(shí),土建已經(jīng)進(jìn)場(chǎng)施工2~3年,所以設(shè)備基礎(chǔ)一般需要放在土建后期進(jìn)行施工。而且土建施工質(zhì)量需要滿足水平度、平行度、預(yù)埋件位置等要求。
開關(guān)柜基礎(chǔ)型鋼的制作是在現(xiàn)場(chǎng)完成的,使用水準(zhǔn)儀進(jìn)行測(cè)量并對(duì)基礎(chǔ)型鋼進(jìn)行找平,將誤差控制在規(guī)范要求范圍內(nèi)。另外,根據(jù)電氣安裝相關(guān)規(guī)范,基礎(chǔ)型鋼應(yīng)通過(guò)接地扁鋼與接地干線進(jìn)行連接,且不少于兩處,接地扁鋼的規(guī)格尺寸應(yīng)符合要求,連接完成后應(yīng)測(cè)量接地電阻值并滿足規(guī)范要求。
安裝開關(guān)柜前,設(shè)備房的裝修工程(包括天、地、墻)應(yīng)基本完成,特別是地面水磨石或石材一定要鋪貼完成,后續(xù)不存在切割、粉刷、噴涂等工程,否則等開關(guān)柜安裝完成后,這些工程有可能對(duì)設(shè)備造成損壞,且影響設(shè)備運(yùn)營(yíng)。
二、重視設(shè)計(jì)交底和圖紙會(huì)審
設(shè)計(jì)交底和圖紙會(huì)審是設(shè)計(jì)人員非常重要的工作,也是圖紙與現(xiàn)場(chǎng)的復(fù)核,對(duì)工程施工的意義十分重大。在設(shè)計(jì)人員進(jìn)行設(shè)計(jì)交底時(shí),項(xiàng)目部技術(shù)人員必須詳細(xì)記錄施工要點(diǎn)、難點(diǎn)、關(guān)鍵點(diǎn),并應(yīng)關(guān)注本工程與以往工程的差異點(diǎn)。在圖紙會(huì)審前,技術(shù)人員應(yīng)仔細(xì)研讀圖紙、全面勘察施工現(xiàn)場(chǎng);梳理現(xiàn)場(chǎng)與圖紙的差異、圖紙中未明確的內(nèi)容、設(shè)備、線管與其他設(shè)備位置沖突等圖紙中影響后期施工甚至返工的內(nèi)容,并在圖紙會(huì)審時(shí),與設(shè)計(jì)人員進(jìn)行充分的溝通,達(dá)成一致意見(jiàn)。
三、設(shè)備倉(cāng)儲(chǔ)和通電前的防護(hù)和除濕
設(shè)備生產(chǎn)地一般離地鐵建設(shè)得較遠(yuǎn),大部分設(shè)備都會(huì)跨省,且由于一條地鐵線車站較多,施工進(jìn)度不一,電氣設(shè)備安裝時(shí)間也不統(tǒng)一,所以為了滿足設(shè)備安裝的及時(shí)性,設(shè)備在安裝前需要進(jìn)行倉(cāng)儲(chǔ),待設(shè)備安裝時(shí),由倉(cāng)庫(kù)直接運(yùn)輸至施工現(xiàn)場(chǎng)。在倉(cāng)儲(chǔ)時(shí),設(shè)備必須包裝完整,放置形式滿足設(shè)備要求,倉(cāng)庫(kù)必須滿足清潔、干燥、通風(fēng)、無(wú)腐蝕性氣體、防雨雪等環(huán)境中,儲(chǔ)存地點(diǎn)應(yīng)該避免周圍環(huán)境劇烈變化。
地鐵車站一般在地下,環(huán)境比較潮濕,且電氣設(shè)備安裝后,一般地鐵線路不能夠做到立即通電運(yùn)行,針對(duì)車站環(huán)境,必須配備足夠的通風(fēng)、抽濕設(shè)備,并采取有效措施,保證整個(gè)施工及調(diào)試驗(yàn)收過(guò)程電氣設(shè)備受到可靠保護(hù),必須做好成品保護(hù)工作,設(shè)備房或設(shè)備安裝環(huán)境做到無(wú)塵、干燥、通風(fēng),適合設(shè)備和材料存放。
四、安裝后封堵及清掃
設(shè)備安裝完成后,應(yīng)對(duì)變電所和配電室進(jìn)行全面清潔。首先應(yīng)對(duì)設(shè)備各隔室進(jìn)行全面清理,帶電體各相之間應(yīng)沒(méi)有雜物,特別是金屬物品。雜物清理完成后,使用吸塵器對(duì)設(shè)備進(jìn)行除塵、清潔,杜絕短路隱患。如果不進(jìn)行徹底清理,極容易發(fā)生設(shè)備短路事故,如某地鐵1號(hào)線由于部分施工單位未對(duì)AC0.4kV開關(guān)柜清理不徹底,施工人員將安裝用的螺絲刀、扳手等遺忘在開關(guān)柜格式內(nèi),從而造成多起短路施工,引起開關(guān)柜爆炸,對(duì)地鐵正常運(yùn)行造成了嚴(yán)重影響。清理完成后,應(yīng)對(duì)開關(guān)柜的上下通道進(jìn)行防火封堵,防止老鼠等小動(dòng)物進(jìn)入,造成設(shè)備短路。
五、區(qū)間電纜轉(zhuǎn)彎半徑
地鐵地下區(qū)間一般在1km左右,高架區(qū)間一般在3km左右,長(zhǎng)的達(dá)到6km,甚至更長(zhǎng)。所以地下^間檢修電源電纜規(guī)格一般為WDZA-YJY23-3X35+2X16、WDZA-YJY23-3X50+2X25,高架區(qū)間檢修電源電纜規(guī)格根據(jù)區(qū)間長(zhǎng)度,規(guī)格不一,一般為WDZA-YJY23-3X70+2X35,區(qū)間距離長(zhǎng)的甚至可以達(dá)到WDZA-YJY23-3X240+2X120。根據(jù)規(guī)范要求,交聯(lián)聚氯乙烯絕緣電力電纜(單芯)最小轉(zhuǎn)彎半徑是電纜直徑的20倍,交聯(lián)聚氯乙烯絕緣電力電纜(多芯)最小轉(zhuǎn)彎半徑是電纜直徑的15倍。而在實(shí)際施工中,由于施工難度較大,滿足轉(zhuǎn)彎半徑要求時(shí),成本較高,施工人員并沒(méi)有按照轉(zhuǎn)彎半徑的要求進(jìn)行施工,導(dǎo)致電纜的鎧裝層和絕緣層損壞。由于區(qū)間環(huán)境較差,且屬于運(yùn)營(yíng)檢修薄弱區(qū)域,鎧裝層和絕緣層損壞對(duì)電纜的使用壽命和安全用電造成嚴(yán)重影響,當(dāng)運(yùn)營(yíng)人員發(fā)現(xiàn)時(shí),可能造成嚴(yán)重后果。所以技術(shù)人員一定要重視區(qū)間檢修電纜的敷設(shè),確保轉(zhuǎn)彎半徑滿足規(guī)范要求。
六、管線預(yù)埋
地鐵低壓電氣施工過(guò)程中,管線焊接和預(yù)埋質(zhì)量非常重要。在施工過(guò)程中,由于施工人員的技術(shù)水平參差不齊,極有可能出現(xiàn)錯(cuò)埋、漏埋和不滿足施工標(biāo)準(zhǔn)、規(guī)范及圖紙要求的現(xiàn)象。做好低壓電氣的管線預(yù)埋,首先,施工前要熟悉圖紙,了解強(qiáng)安裝部位、標(biāo)高和管線走向等,仔細(xì)復(fù)合預(yù)埋管線的位置、長(zhǎng)度和型號(hào)規(guī)格等,同時(shí)對(duì)鋼管的管口處理、焊接和防腐等進(jìn)行檢查;其次,要加強(qiáng)質(zhì)量意識(shí)教育。向作業(yè)人員解釋并著重強(qiáng)調(diào)電氣線管預(yù)埋的重要性及預(yù)埋不合格的安全隱患,提高每一位作業(yè)人電氣預(yù)埋的質(zhì)量意識(shí);然后,向作業(yè)人員進(jìn)行明確的技術(shù)交底,使作業(yè)人員謹(jǐn)記管線預(yù)埋的質(zhì)量要求,有目的地進(jìn)行施工。最后,技術(shù)人員平時(shí)要多下現(xiàn)場(chǎng),只有在現(xiàn)場(chǎng)檢查中才能夠發(fā)現(xiàn)施工中存在的問(wèn)題,只要發(fā)現(xiàn)施工質(zhì)量問(wèn)題,必須立即要求整改,并跟蹤到底,直至施工質(zhì)量滿足要求為止;定期分析低壓電氣安裝中出現(xiàn)的質(zhì)量問(wèn)題,找出主要原因,制定相應(yīng)對(duì)策。
結(jié)語(yǔ)
低壓電氣安裝工程作為一項(xiàng)復(fù)雜的系統(tǒng)工程,是地鐵施工的重要組成部分。低壓電氣安裝工程質(zhì)量將會(huì)對(duì)地鐵工程的施工總體質(zhì)量產(chǎn)生直接影響,并且與乘客的乘車環(huán)境具有直接的關(guān)系。所以,在地鐵低壓電氣安裝時(shí),一定要嚴(yán)格根據(jù)規(guī)范和施工工藝要求進(jìn)行安裝,針對(duì)施工中存在的問(wèn)題,采取相應(yīng)的對(duì)策進(jìn)行解決,從而提高地鐵低壓電氣安裝工程質(zhì)量。
參考文獻(xiàn)
[1]陳英健.10kV配電室安裝的施工控制[J].中國(guó)新技術(shù)新產(chǎn)品,2012(21):139.
【關(guān)鍵詞】:中壓電力電纜;施工過(guò)程;注意事項(xiàng)
1、中低壓敷設(shè)時(shí)的注意事項(xiàng)
中低壓電纜敷設(shè)即將相應(yīng)數(shù)量的電纜以一定的技術(shù)進(jìn)行鋪設(shè),建立起安全、合理、有效的電力系統(tǒng)。在進(jìn)行中壓電力電纜敷設(shè)的過(guò)程中,首先要保證中壓電力電纜的質(zhì)量以及完整性,防止電纜在運(yùn)輸過(guò)程中或外力破壞下發(fā)生彎曲、纜線破損等情況,以高質(zhì)量確保電纜敷設(shè)的有效性;其次,盡可能減輕電纜纜線與支架、地面等部分的麻擦程度,避免過(guò)度損耗破壞電纜性能。
2、中低壓安裝時(shí)的注意事項(xiàng)
中壓電力電纜的安裝主要包括電纜終端附件安裝和電纜中間接頭安裝。中壓電力電纜終端附件及中間接頭安裝是中壓電力電纜施工過(guò)程中最為薄弱的環(huán)節(jié),安裝質(zhì)量將直接影響到整個(gè)配電系統(tǒng)的安全運(yùn)行。據(jù)不完全統(tǒng)計(jì),因安裝質(zhì)量不佳引起的線路故障約占整個(gè)線路故障的80%以上。對(duì)此,在中壓電力電纜施工過(guò)程中應(yīng)給予足夠的重視,確保高質(zhì)量完成中壓電力電纜的安裝工作。中壓電力電纜終端附件通常可分為冷縮電纜附件和熱縮電纜附件兩種。根據(jù)電纜用材料的特性、用戶要求和目前施工條件,建議選擇冷縮電纜附件,雖然其價(jià)格較高,但安全性也高一些。中壓電力電纜終端附件安裝的流程為:剝除電纜外護(hù)套拆除鋼帶鎧裝層(可選,若有同時(shí)檢查單芯電纜的鎧裝材料是否為非磁性金屬帶)剝除電纜隔離套(可選)焊接銅帶屏蔽接地線(做好線芯標(biāo)志線)剝除絕緣屏蔽層(10KV電纜絕緣半導(dǎo)電屏蔽層一般為可剝離型,容易剝除;35KV電纜絕緣半導(dǎo)電屏蔽層為不可剝離型,處理時(shí)應(yīng)特別注意不要損傷絕緣層)清理絕緣表面安裝半導(dǎo)電管安裝分支手套剝除絕緣層和導(dǎo)體屏蔽層(削成鉛筆頭狀)安裝絕緣套管和接線端子。在中壓電力電纜終端附件安裝過(guò)程中應(yīng)注意以下方面:
銅帶接地線應(yīng)焊接牢固;剝除導(dǎo)體屏蔽層時(shí)切勿損傷導(dǎo)體,造成導(dǎo)體毛刺,引起電纜局部放電量超標(biāo);接線端子應(yīng)和電纜導(dǎo)體材料匹配,鋁芯導(dǎo)體時(shí)應(yīng)采用質(zhì)量過(guò)硬的銅鋁過(guò)渡端子,且端子內(nèi)灌裝導(dǎo)電膏,壓接時(shí)由端子末端開始,且壓接到位;電纜絕緣與端子的接觸面應(yīng)處理完美,保證密封完好,否則將因此產(chǎn)生很多故障點(diǎn)。
3、接地時(shí)的注意事項(xiàng)
在以往中壓電力電纜線路故障中,經(jīng)常出現(xiàn)因電纜某一相嚴(yán)重發(fā)熱,導(dǎo)致短路的案例。解剖故障電纜后發(fā)現(xiàn),電纜絕緣線芯完好,銅帶上有灼傷未透,但其余部分均已灼傷炭化,種種跡象表明是由外向里燒,這說(shuō)明電纜導(dǎo)體本身在運(yùn)行中并未發(fā)生問(wèn)題,而是其他原因造成電纜發(fā)熱炭化。通過(guò)分析確認(rèn),當(dāng)中壓電力電纜在交變電壓下運(yùn)行時(shí),導(dǎo)體中通過(guò)的交變電流會(huì)產(chǎn)生交變磁場(chǎng),磁場(chǎng)產(chǎn)生的磁力線與導(dǎo)體相連,同時(shí)也與金屬護(hù)套(屏蔽層和鎧裝層)相通,這樣在金屬護(hù)套中就產(chǎn)生感應(yīng)電壓,如果感應(yīng)電壓過(guò)高,而在中壓電力電纜實(shí)際施工過(guò)程中又未能進(jìn)行安全接地,則會(huì)在金屬護(hù)套中產(chǎn)生較大的感應(yīng)電流(環(huán)流),使電纜嚴(yán)重發(fā)熱,導(dǎo)致短路故障。因此,為了確保系統(tǒng)穩(wěn)定可靠安全運(yùn)行,必須根據(jù)中壓電力電纜金屬護(hù)套中產(chǎn)生的感應(yīng)電壓和環(huán)流采取正確安全的接地方式,以降低系統(tǒng)線路發(fā)熱和短路故障風(fēng)險(xiǎn)。
4、中壓電力電纜施工中的防范策略
4.1從施工材料著手杜絕中壓電力電纜的質(zhì)量問(wèn)題
首先,應(yīng)當(dāng)對(duì)供貨商的信譽(yù)問(wèn)題進(jìn)行充分考慮,以信譽(yù)良好及纜線質(zhì)量具有一定保障的商家為優(yōu)選,并與其建立長(zhǎng)期穩(wěn)定的合作關(guān)系,為日后施工作業(yè)的開展提供相應(yīng)的便利條件;其次,還應(yīng)對(duì)電纜的型號(hào)、長(zhǎng)度等相關(guān)因素進(jìn)行結(jié)合考量,對(duì)施工現(xiàn)場(chǎng)的實(shí)際情況做出準(zhǔn)確評(píng)估,并根據(jù)評(píng)估結(jié)果進(jìn)行電纜型號(hào)、長(zhǎng)度等因素的確定;最后,溫度對(duì)電纜的影響也是一項(xiàng)引起足夠重視的因素,在進(jìn)行電纜選擇時(shí),為對(duì)其穩(wěn)定性形成牢固的保障,應(yīng)在實(shí)際所需的長(zhǎng)度基礎(chǔ)上,選擇長(zhǎng)度相對(duì)更長(zhǎng)的纜線。
4.2電纜敷設(shè)安全管理
為保證中壓電力電纜敷設(shè)施工的安全性,需注意以下幾點(diǎn):盡可能從電纜橋架開始引導(dǎo),減少電纜與支架、地面之間的摩擦力;電纜施工人員應(yīng)當(dāng)重視施工質(zhì)量的控制,在保證施工速度的同時(shí),防止由于電纜彎曲半徑過(guò)小,所導(dǎo)致的電纜損傷;在電纜溝、隧道敷設(shè)電纜施工中,要求預(yù)先設(shè)置支架,避免電纜出現(xiàn)交叉,使用機(jī)械來(lái)牽引電纜,并防止溝底部角落摩擦擠壓損傷電纜;施工中需設(shè)置路障,以往受到外界因素的干擾,導(dǎo)致電纜損傷。
4.3質(zhì)量驗(yàn)收和運(yùn)行管理
中壓電力電纜工程的驗(yàn)收,是項(xiàng)目施工的最后工序,同時(shí)也是檢測(cè)施工質(zhì)量、確認(rèn)項(xiàng)目是否達(dá)標(biāo)的關(guān)鍵。對(duì)于中壓電力電纜施工質(zhì)量的驗(yàn)收管理,通常由單向工程進(jìn)行,最終由全部的竣工驗(yàn)收來(lái)完成。中壓電力電纜竣工并正式投入使用之后,還需要繼續(xù)重視其運(yùn)行安全管理的加強(qiáng),做好相關(guān)的檢測(cè)、維護(hù)工作,通過(guò)對(duì)用戶進(jìn)行回訪,實(shí)現(xiàn)實(shí)時(shí)掌控。
結(jié)語(yǔ)
針對(duì)中壓電力電纜的施工過(guò)程具有電壓高、屏蔽多、線路長(zhǎng)、現(xiàn)場(chǎng)環(huán)境惡劣、施工要求高等特點(diǎn),本文對(duì)施工過(guò)程中敷設(shè)、安裝、接地時(shí)應(yīng)注意的事項(xiàng)進(jìn)行了詳細(xì)介紹。但中壓電力電纜的敷設(shè)、安裝、接地方式存在多種情況,且多采用隱蔽性較大的埋地敷設(shè)和電纜溝敷設(shè)方式,造成電纜故障的復(fù)雜多樣,增加電纜故障點(diǎn)的分析、定位、查找、修復(fù)的難度,因此電纜施工人員和管理人員的專業(yè)素養(yǎng)和基本技能對(duì)高質(zhì)量完成電纜的敷設(shè)、安裝、接地等工作十分關(guān)鍵,在施工和管理時(shí)必須規(guī)范操作、按圖施工,掌握電纜敷設(shè)過(guò)程中的技術(shù)要點(diǎn),避免故障的產(chǎn)生。
【參考文獻(xiàn)】 :
【關(guān)鍵詞】110kV變電站;進(jìn)線電纜;施工方法
隨著改革開發(fā)的逐漸深入以及城市建設(shè)的加速,涌人城市的人口日益增多,使城市化進(jìn)程愈來(lái)愈快,這就要求相關(guān)部門應(yīng)摒棄先前存在但如今已不能適應(yīng)現(xiàn)代城市發(fā)展需求的輸電網(wǎng)絡(luò),并采取有效措施對(duì)其進(jìn)行改革,且大多數(shù)供電方采用的改革方式均為改用110kV變電站的輸電線路,然而110kV屬單芯電纜,因此我們應(yīng)注意對(duì)限制其護(hù)層感應(yīng)的電壓引起重視,同時(shí)為避免過(guò)電壓造成電纜護(hù)層擊穿現(xiàn)象發(fā)生,我們?cè)趯?duì)其接地方式進(jìn)行設(shè)計(jì)、安裝時(shí),應(yīng)注意任一環(huán)節(jié)都不應(yīng)出現(xiàn)錯(cuò)漏,如果電纜金屬護(hù)層多點(diǎn)接地一旦出現(xiàn)故障,由于故障較難測(cè)尋原因,將會(huì)使線路修復(fù)難以完成,從而造成大量電量損失現(xiàn)象。而變電站的進(jìn)線電纜施工的質(zhì)量直接關(guān)系到變電站能否正常工作,關(guān)系到人們的直接利益,和人們的生活息息相關(guān),因此我們要對(duì)110kV變電站進(jìn)線電纜工程的施工方法進(jìn)行高度的關(guān)注。
1 關(guān)于電纜故障的分析
對(duì)于電纜故障而言,由于電纜有高壓電纜與低壓電纜之分。因此,我們發(fā)現(xiàn)高壓電纜和低壓電纜的故障有許多不同之處。高壓電纜的故障一般都是以運(yùn)行故障為主,而且大多數(shù)是高阻故障,高阻故障又分為泄漏和閃絡(luò)兩大類型。而低壓電纜故障常見(jiàn)的有接地故障、短路故障以及斷路故障三種,這三種常見(jiàn)的三芯電纜故障類型具體表現(xiàn)在以下幾個(gè)方面:①一相或多相接地;②二相線間短路;③相線間完全短路;④ 一相斷線或多相斷線。我所談到的電流熱效應(yīng)法進(jìn)行電纜故障的速查主要也是查找低壓電纜的故障。因此,對(duì)低壓電纜在運(yùn)行中所具有的特點(diǎn)進(jìn)行分析是非常必須的,其在實(shí)際使用過(guò)程中低壓電纜與高壓電纜對(duì)比具有以下特點(diǎn):
(1)敷設(shè)的隨意性較大,路徑敷設(shè)不清楚,顯得電纜線路的混亂;
(2)相對(duì)于高壓電纜而言,其敷設(shè)中埋深較淺,容易受到外力的作用而發(fā)生故障;
(3)低壓電纜一般較短,幾十米到幾百米不等,而高壓電纜一般在幾百米到幾公里,對(duì)電纜故障的檢查產(chǎn)生了一定的阻力;
(4)低壓電纜的絕緣強(qiáng)度要求較低,處理故障接頭時(shí)工藝也較簡(jiǎn)單;相反,高壓電力對(duì)于絕緣強(qiáng)度的要求較高,處理故障接頭時(shí)的工藝要求較為復(fù)雜;
(5)無(wú)論是低壓電纜還是高壓電纜,電纜故障點(diǎn)都有十分明顯的燒焦現(xiàn)象;
(6)低壓電纜由于所帶負(fù)載的變化較大,而且相間常常出現(xiàn)不平衡的情況,容易發(fā)熱,從而導(dǎo)致電纜發(fā)生故障的情況就很常見(jiàn)了;高壓電力由于負(fù)載的變化較小,相間相對(duì)較為平衡且不容易發(fā)熱,發(fā)生故障的情況較少,但若發(fā)生電力故障,維修的工序也就更為復(fù)雜。
2 電纜應(yīng)用的注意事項(xiàng)
在現(xiàn)代電纜工程中,主要采用的礦物絕緣電纜,本文主要對(duì)礦物絕緣電纜的注意事項(xiàng)進(jìn)行分析。
(1)敷設(shè)事項(xiàng)。由于礦物絕緣電纜具有較大的硬度,在進(jìn)線敷設(shè)時(shí),盡量防止交叉,在施工之前,應(yīng)結(jié)合設(shè)計(jì)圖紙的要求,繪制好敷設(shè)的走向圖,并對(duì)電纜規(guī)格、走向、交叉間距、長(zhǎng)度、中間連接位置、根數(shù)等進(jìn)線認(rèn)真核對(duì)。在敷設(shè)時(shí),必須在專用放線架上進(jìn)線敷設(shè)。在進(jìn)線包裝拆除時(shí),避免小刀將包裝層劃穿,防止銅護(hù)套遭到損傷,在終端、中間的練級(jí)頭,必須留有一定的電纜長(zhǎng)度,以便于施工。
(2)對(duì)電纜回路進(jìn)線編號(hào)、粘貼標(biāo)志。在中間接頭處、始點(diǎn)、終點(diǎn)處、穿墻處,均要設(shè)置標(biāo)志牌,對(duì)各回路進(jìn)線相序、編號(hào),防止因接頭和回路過(guò)多,而導(dǎo)致無(wú)法辨別,使得相序、回路出現(xiàn)連接錯(cuò)誤。
(3)降低渦流的損耗。許多工程中的礦物絕緣電纜,大多采用單芯電纜構(gòu)成回路,在電纜固定金具里極易產(chǎn)生相應(yīng)的感應(yīng)渦流。若渦流量過(guò)大,將導(dǎo)致大量增加渦流損耗,加快電纜固定金具的老化速度。因此,在施工過(guò)程中,盡量防止產(chǎn)生渦流,或者采用措施使渦流損耗最小化。
(4)電纜防潮。在進(jìn)線電纜校直時(shí),應(yīng)防止損傷銅護(hù)套 在進(jìn)行敷設(shè)之前,應(yīng)對(duì)絕緣電阻值、銅護(hù)套的損傷情況及是否進(jìn)線認(rèn)真檢測(cè)。若發(fā)現(xiàn)問(wèn)題,應(yīng)及時(shí)選擇石蠟進(jìn)線密封。
(5)電纜彎曲。在敷設(shè)進(jìn)出配電柜、穿越墻洞、T形彎、電氣豎井、L形彎等空間較為窄小、彎曲度較大時(shí),必須注意均衡用力:在進(jìn)行彎曲處處理時(shí),根據(jù)安裝規(guī)范的力度與方法冷彎,禁止采用人工強(qiáng)行彎曲,以避免損傷銅護(hù)套;其六,制作礦物絕緣電纜的質(zhì)量控制。因礦物絕緣電纜與普通電纜相比,其特殊性較為明顯,在完成敷設(shè)之后,選擇搖表對(duì)絕緣電阻進(jìn)行測(cè)量,曾發(fā)生過(guò)絕緣電阻過(guò)低的現(xiàn)象,經(jīng)過(guò)分析和研究,主要是由于電纜在制作過(guò)程中出現(xiàn)的質(zhì)量缺陷,而引起的電阻過(guò)低現(xiàn)象。因此,電阻測(cè)量必須達(dá)到要求、規(guī)范,或除濕處理。在剝除銅護(hù)套的過(guò)程中,防止損傷線芯。在剝除鎂粉時(shí),必須選擇干凈的棉紗,以清理干凈剩余的粉末;電纜頭制作必須選擇專用工具、封口膏、硅膠等。
3 電纜接地保護(hù)
(1)接地保護(hù)類型。主要分為三種:①保護(hù)接地。對(duì)接地進(jìn)行保護(hù)主要是為確保人身和設(shè)備的安全,使電氣設(shè)備在運(yùn)行過(guò)程中,將其不帶電的金屬構(gòu)件或金屬外殼,利用接地裝置同船體或大地進(jìn)行連接;②保護(hù)接零,主要是在三相四線制的系統(tǒng)之中,利用中性線或?qū)Ь€連接電氣設(shè)備的金屬構(gòu)件與外殼;③工作接地.這主要是確保電氣設(shè)備無(wú)論出于正常或異常的情況下,都能正常、可靠的工作,利用接地裝置同船體或大地進(jìn)行連接。
(2)施工現(xiàn)場(chǎng)接地保護(hù)中的問(wèn)題。在平常的檢測(cè)中,接地保護(hù)主要有以下問(wèn)題:①在同一電網(wǎng)中,同時(shí)選擇接地保護(hù)和接零保護(hù);②少于三處的重復(fù)接地零線,一般為始端、中端和末端,在每處的接地裝置,接地電阻必須大于lOΩ;③工作零線截面小于保護(hù)零線截面;④不結(jié)合規(guī)定接零、接地范圍,對(duì)電氣設(shè)備和設(shè)施進(jìn)行合理、可靠的接地;⑤選擇不得當(dāng)?shù)慕拥匮b置;⑥進(jìn)行接地裝置的鋪設(shè)時(shí),達(dá)不到要求;⑦未根據(jù)規(guī)范連接接地體;⑧接地裝置未達(dá)到所要求的接地電阻值。
(3)施工現(xiàn)場(chǎng)正確的接地保護(hù)。根據(jù)有關(guān)規(guī)定,同一供電系統(tǒng)不能同時(shí)選擇接地系統(tǒng),若直接與公用變壓器進(jìn)行接線,施工現(xiàn)場(chǎng)必須采用專門電源中性點(diǎn)、零線保護(hù)的三相四線制配電系統(tǒng)進(jìn)行接地。若外電線路和施工現(xiàn)場(chǎng)線路存在于同一供電網(wǎng)內(nèi),電氣設(shè)備結(jié)合當(dāng)?shù)氐膶?shí)際需求做保護(hù)接地。因此,施工現(xiàn)場(chǎng)必須根據(jù)電源來(lái)源的情況,來(lái)進(jìn)行保護(hù)接地。主要表現(xiàn)在四個(gè)方面:① 施工現(xiàn)場(chǎng)用電,必須選擇中性點(diǎn)進(jìn)行直接接地。②施工現(xiàn)場(chǎng)的重復(fù)接地裝置,即接地體應(yīng)選擇兩根伊桑圓鋼、鋼管后角鋼,禁止使用螺紋鋼或者鋁導(dǎo)體。兩個(gè)接地體之間應(yīng)保持5m左右的水平距離,控制好接地體的長(zhǎng)度,一般為2.5m為宜,控制好接地極的埋深,通常大于0.7m的頂端距地距離為宜。③選擇焊接的方式連接接地體,焊接應(yīng)該牢固且無(wú)虛焊。④在進(jìn)行重復(fù)接地時(shí),應(yīng)該注意幾個(gè)方面:a.重復(fù)接地總配電箱之后,禁止在設(shè)備、線路任意點(diǎn)連接工作零線,禁止通過(guò)任何的開關(guān)。若開關(guān)內(nèi)、配電箱內(nèi)設(shè)置有端子板時(shí),金屬箱體同端子板必須進(jìn)行絕緣。b.施工所用的開關(guān)箱、配電箱、移動(dòng)箱,應(yīng)在堅(jiān)固支架上進(jìn)行裝設(shè),不允許地面拖拉。c.施工過(guò)程中的開關(guān)箱,應(yīng)該采用一機(jī)一閘,禁止設(shè)置有分路開關(guān),應(yīng)該講漏電保護(hù)器裝設(shè)在開關(guān)柜、總配電箱內(nèi)。
4 結(jié)束語(yǔ)
在電力工程中,電纜的進(jìn)線好壞關(guān)系著整個(gè)工程的用電質(zhì)量、用電安全,因此在110kV變電所施工時(shí),要保證電纜的合理進(jìn)線,選擇合格的電纜,嚴(yán)格按照注意事項(xiàng)進(jìn)線,保證電纜成功進(jìn)線。
參考文獻(xiàn):
[1]彭茗,胡義軍,王友平,等.GIS電氣設(shè)備在非城區(qū)小型化變電站的布置應(yīng)用[J].陜西電力,2010(2).
Abstract: The quality of power cable engineering construction is the guarantee that power grid can operate with safety, stability, reliability and economy. In order to improve quality, we should be elaborate organization and strict construction, according to design drawings and construction standard, and prevent quality problems so as to achieve the purpose of improving reliability and stability of power system.
關(guān)鍵詞:電纜敷設(shè);施工要點(diǎn);質(zhì)量控制
Key words: cable placing;construction points;quality control
中圖分類號(hào):TM246 文獻(xiàn)標(biāo)識(shí)碼:A 文章編號(hào):1006-4311(2011)23-0081-01
1電纜的敷設(shè)方式
電纜的敷設(shè)方式常見(jiàn)有以下幾種:直埋敷設(shè)、電纜溝敷設(shè)、排管敷設(shè)、電纜橋架敷設(shè)。
1.1 直埋敷設(shè)施工中應(yīng)注意:電纜溝深不小于800mm,挖完電纜溝后應(yīng)將溝底鏟平夯實(shí);電纜埋深要求不小于700mm,電纜的上下各有100mm砂子,砂子要均勻密實(shí),上面還要蓋紅磚或混凝土蓋板,其覆蓋寬度應(yīng)超過(guò)電纜兩側(cè)各50mm。直埋電纜必須采用鎧裝電纜。電纜距建筑物外墻和電線桿不小于0.6m,距排水明溝、道路與樹木不小于1.0m,與熱力管溝相距不小于2.0m。不得將電纜平行敷設(shè)在各種管路的正下方或正上方。地面上在電纜拐彎處或進(jìn)建筑物處要埋設(shè)方向樁,以備日后施工或檢修時(shí)參考。直埋電纜一般限于6根以內(nèi),超過(guò)6根就應(yīng)采用電纜溝敷設(shè)方式。
1.2 電纜溝敷設(shè)在電纜溝內(nèi)預(yù)埋金屬支架,電纜支架應(yīng)安裝牢固,橫平豎直。電纜多時(shí),可以在兩側(cè)都預(yù)埋支架。如果電纜非常多,則可用電纜隧道敷設(shè),油田建設(shè)工程中應(yīng)用不多。采用電纜溝敷設(shè)方式施工中,應(yīng)該注意低壓電纜與高壓電纜盡可能分開設(shè)置在電纜溝內(nèi)支架的兩側(cè)??刂齐娎|與電力電纜也盡可能分開設(shè)置在電纜溝支架的兩側(cè)。如果只能在同―側(cè)時(shí),應(yīng)該遵守高壓電力電纜、低壓電力電纜、控制電纜、信號(hào)電纜在支架上從上至下排列的原則。金屬支架的間距為1m。
1.3 電纜排管敷設(shè)電纜排管敷設(shè)是指電纜穿石棉水泥管、塑料管或鋼管等成排地敷設(shè)于地下。管內(nèi)穿電纜時(shí)事先在管內(nèi)穿鉛絲將電纜拉人管內(nèi)。在施工主要要求穿電纜時(shí)宜用滑輪引導(dǎo)電纜,不得刮傷電纜。排管中管子的接頭錯(cuò)開,以便平行敷設(shè)緊湊,在接頭處應(yīng)用水泥筑為整體。
1.4 電纜橋架敷設(shè)電纜橋架的配線方式,廣泛用于油田聯(lián)合站、注水站、轉(zhuǎn)油站、變電站等建設(shè)工程中。電纜在橋架上應(yīng)單層敷設(shè),排列整齊,在電纜的首端、末端、分支處應(yīng)掛標(biāo)志牌;不得有交叉,拐彎處應(yīng)以最大截面電纜允許彎曲半徑為準(zhǔn)。不同等級(jí)電壓的電纜應(yīng)分層敷設(shè),高壓電纜敷設(shè)在上層;同等級(jí)電壓的電纜敷設(shè)時(shí),水平凈距不得小于350mm。電纜橋架的特點(diǎn)是結(jié)構(gòu)簡(jiǎn)單,安裝方便,耐腐蝕。
2電力電纜的敷設(shè)與安裝
電力電纜同架空線路一樣,也是輸送和分配電能的。其敷設(shè)、安裝過(guò)程如下:
2.1電力電纜的敷設(shè)準(zhǔn)備工作:
2.1.1 檢查所敷設(shè)電纜型號(hào)、規(guī)格與設(shè)計(jì)圖紙是否相同,電纜外觀是否有扭曲、壞損及漏油、滲油現(xiàn)象。
2.1.2 檢查電纜是否受潮,可用火燒法或油浸法。用兆歐計(jì)搖測(cè)電纜的絕緣電阻,低壓電纜正常值應(yīng)大于10MΩ。高壓電纜的絕緣電阻:3kV電力電纜為200 MΩ;6kV電力電纜為400 MΩ;10KV電力電纜為50 MΩ。
2.1.3 按設(shè)計(jì)和實(shí)際路徑計(jì)算每根電纜的長(zhǎng)度,合理安排每盤電纜,減少電纜接頭。
2.1.4 電纜線路所需敷設(shè)的電纜保護(hù)管應(yīng)加工好并放置現(xiàn)場(chǎng)。電纜保護(hù)管的加工應(yīng)符合以下要求:①管口應(yīng)無(wú)毛剌和尖銳棱角,管口宜做成喇叭形;②電纜管在彎制后,不應(yīng)有裂縫和顯著的凹癟現(xiàn)象;電纜管的彎曲半徑不應(yīng)小于所穿入電纜的最小允許彎曲半徑。
3施工中應(yīng)注意的問(wèn)題
3.1 大電流電力電纜引發(fā)的渦流只要在電力電纜周圍形成鋼(鐵)性閉合回路的,都有可能形成渦流,在大電流電力電纜系統(tǒng)中,渦流更大。在電力電纜施工中,有采用鋼支架的,有采用鋼質(zhì)保護(hù)管的,有采用電纜卡與架空敷設(shè)的,因此在電纜施工時(shí),必須采取措施,使電纜周圍不能形成鋼(鐵)性閉合回路,防止電纜引起渦流現(xiàn)象發(fā)生。
3.2 電力電纜的轉(zhuǎn)彎引起的機(jī)械性損傷電力電纜在施工中,轉(zhuǎn)彎角度不能過(guò)大,否則會(huì)導(dǎo)體內(nèi)部受到機(jī)械損傷,而機(jī)械損傷因被電纜絕緣強(qiáng)度下降,直到出現(xiàn)故障。
3.3 電力電纜防潮中、低壓電力電纜故障大部分為電纜中間接頭和終端頭故障,而中間接頭和終端頭故障則大部分是因密封不良,潮氣侵入而造成絕緣強(qiáng)度下降,中、低壓電力電纜網(wǎng)多采用樹枝狀供電方式,電纜終端頭數(shù)量較多,因此把好電纜終端頭和中間接頭堵漏密封關(guān)是保證電纜安全可靠運(yùn)行的重要措施之一。
3.4 電力電纜防火問(wèn)題電纜本身易燃,而且火勢(shì)不易在短時(shí)間內(nèi)撲滅。為防止電纜著火及火勢(shì)擴(kuò)大,在電纜穿過(guò)豎井、墻壁、樓板或進(jìn)入電氣盤、柜的孔洞處,用防火堵料密實(shí)封堵;在重要的電纜溝中,按要求分段或用軟質(zhì)耐火材料設(shè)置阻火墻;對(duì)重要回路的電纜,可單獨(dú)敷設(shè)于專門的溝道中或耐火封閉槽盒內(nèi),或?qū)ζ涫┘臃阑鹜苛?、防火包帶;在封堵電纜孔洞時(shí),封堵應(yīng)嚴(yán)實(shí)可靠,不應(yīng)有明顯的裂縫和可見(jiàn)的孔隙,孔洞較大者應(yīng)加耐火襯板后再進(jìn)行封堵。
3.5 電力電纜施工中的安全問(wèn)題施工中堅(jiān)持安全第一的原則。施工人員必須正確佩戴安全帽,并隨身攜帶手套,方便拉電纜時(shí)使用防止拉傷手;電纜架應(yīng)安裝牢固,放電纜前應(yīng)進(jìn)行檢查;不能站在電纜支架上拉電纜或進(jìn)行其它的不安全行為;運(yùn)輸電纜盤時(shí)應(yīng)有防止電纜盤在車上滾動(dòng)的措施,盤上的電纜頭應(yīng)固定好,卸電纜盤時(shí)嚴(yán)禁從車上直接推下;敷設(shè)電纜時(shí),電纜盤應(yīng)架設(shè)牢固平穩(wěn),盤邊緣距地面不得小于100mm,電纜應(yīng)從盤的上方引出,引出端頭的鎧裝如有松弛則應(yīng)綁緊;敷設(shè)電纜應(yīng)有專人指揮,統(tǒng)一行動(dòng),不得在無(wú)指揮時(shí)隨意拉引電纜;在高處敷設(shè)電纜時(shí),應(yīng)有高處作業(yè)措施;電纜通過(guò)孔洞、管子、設(shè)備時(shí),兩側(cè)必須有監(jiān)護(hù)人,入口側(cè)應(yīng)防止電纜被卡或手被帶入孔內(nèi),出口側(cè)人員不得在正面接引電纜;敷設(shè)電纜時(shí),拐彎處的施工人員應(yīng)站在電纜外側(cè);敷設(shè)電纜時(shí),臨時(shí)打開的孔應(yīng)設(shè)有遮欄或警告標(biāo)志牌,施工完后封回。
參考文獻(xiàn):
[1]中華人民共和國(guó)國(guó)家標(biāo)準(zhǔn).GB 50168-2006電氣裝置安裝工程電纜線路施工及驗(yàn)收規(guī)范[S].中華人民共和國(guó)建設(shè)部,2006,(7).
【關(guān)鍵詞】配電工程;安裝管理 質(zhì)量控制
1.土建施工管理
土建施工應(yīng)盡量考慮到電氣安裝工作,在土建施工時(shí),負(fù)責(zé)電氣專業(yè)的工作人員應(yīng)密切配合,嚴(yán)格把關(guān)與配電室控制盤、配電柜安裝有關(guān)建筑物(構(gòu)筑物)尺寸、位置、預(yù)埋件位置是否正確,是否牢固等。在基礎(chǔ)型鋼的制作與安裝方面,基礎(chǔ)型鋼一般是現(xiàn)場(chǎng)制作;施工前,施工人員依據(jù)設(shè)計(jì)藍(lán)圖尺寸并結(jié)合訂貨圖中每面控制盤和高低壓柜的尺寸進(jìn)行核實(shí)后下料,以避免因設(shè)計(jì)疏忽或筆誤造成偏差。為了承重和增強(qiáng)穩(wěn)定性,低壓配電柜的底座一般采用10# 槽鋼,拼裝、焊接加工后按平面布置圖上的尺寸位置將槽鋼擺放在正確的安裝位置,確定盤間誤差在可控范圍,以防電氣施工時(shí)因尺寸誤差給母線橋連接安裝帶來(lái)麻煩。此外,還要注意基礎(chǔ)型鋼的固定與接地?;A(chǔ)型鋼固定前應(yīng)與土建專業(yè)確定最后室內(nèi)地平的標(biāo)高,以型鋼底座的標(biāo)高高于地平標(biāo)高2cm 左右為宜。每組型鋼底座應(yīng)有不少于2 處的接地,接地材料一般選用鍍鋅扁鋼直接與接地干線相連,接地干線的接地電阻應(yīng)符合設(shè)計(jì)要求。另外型鋼的內(nèi)側(cè)或接地扁鋼上需焊幾組接地螺栓,因?yàn)楦邏汗駜?nèi)的接地線要與此相連,要求使用專用鍍鋅螺栓。
2.高低壓柜的安裝管理
2.1 設(shè)備進(jìn)場(chǎng)前的檢查
設(shè)備的開箱檢查應(yīng)由安裝單位、供貨單位、總包單位、以及監(jiān)理共同進(jìn)行。檢查時(shí)按照設(shè)備清單、施工圖紙、設(shè)備技術(shù)資料逐一核對(duì)設(shè)備本體及附件、備件,確保符合設(shè)計(jì)圖紙的要求;附件、備件齊全;產(chǎn)品合格證件、技術(shù)資料、說(shuō)明書齊全。盤、柜本體及外觀檢查應(yīng)注意以下幾個(gè)方面:外觀應(yīng)無(wú)損傷、無(wú)變形,盤、柜表面的各元器件完好,無(wú)遺漏;表面油漆完整無(wú)損,漆膜色澤均勻、平整光滑,用肉眼看不到劃痕、皺痕、修復(fù)痕跡;盤、柜中所有的電鍍件的鍍層,不能有起皮、脫落、生銹等現(xiàn)象;柜門應(yīng)能靈活轉(zhuǎn)動(dòng),在轉(zhuǎn)動(dòng)的過(guò)程中不應(yīng)損壞漆膜,不能使電器元件受到?jīng)_擊,上鎖后不應(yīng)有明顯的晃動(dòng)。
2.2 設(shè)備保存與搬運(yùn)
盤、柜應(yīng)存放在室內(nèi)或能避雨、雪、風(fēng)、沙的干燥場(chǎng)所。若設(shè)備存放在室外,應(yīng)覆蓋塑料布,做好防潮工作。對(duì)有特殊保管要求的裝置性設(shè)備和電氣元件,應(yīng)按規(guī)定保管,設(shè)備嚴(yán)禁倒立。檢查運(yùn)輸路徑,確定合適的吊運(yùn)方案。由吊裝設(shè)備及起重人員配合配電屏運(yùn)送人員至安裝現(xiàn)場(chǎng)裝卸;吊裝時(shí),按照盤、柜安裝的倒序裝車,即車尾位置的盤、柜為首先進(jìn)入室內(nèi),車頭位置的盤、柜為最后進(jìn)入室內(nèi),以方便盤、柜進(jìn)入室內(nèi)的安裝施工。盤、柜二次搬動(dòng)時(shí),搬運(yùn)設(shè)備齊全,人員充足,統(tǒng)一指揮進(jìn)行。
2.3 設(shè)備的就位及安裝
依據(jù)施工圖紙,核實(shí)基礎(chǔ)坐標(biāo)無(wú)誤,清理施工現(xiàn)場(chǎng)。盤、柜進(jìn)入室內(nèi),應(yīng)按安裝順序落于基礎(chǔ)上,并留有足夠的間隔,以便于施工中的就位與找正,盤、柜的四角都應(yīng)落于基礎(chǔ)上,防止傾斜造成變形。單列盤、柜的就位。單列盤、柜的安裝就位靈活性大,可由基礎(chǔ)的一側(cè)逐一安裝,也可從基礎(chǔ)中間找出基準(zhǔn)點(diǎn),由中間向兩邊延伸安裝。將基準(zhǔn)柜按照設(shè)計(jì)位置就位后找正,單獨(dú)盤、柜進(jìn)行柜面和側(cè)面的垂直度的調(diào)整,可加裝墊鐵的方法解決,每面柜加裝墊鐵不能超過(guò)三片。用線墜檢查垂直度符合要求,然后進(jìn)行下一塊盤、柜的就位找正。從第二塊盤、柜依次找正并固定于前一塊盤、柜,用盤間螺栓連接固定依次進(jìn)行。兩列及以上的盤、柜就位。兩列及以上的盤、柜就位,應(yīng)考慮母線橋的搭接,優(yōu)先安裝母線橋搭接的兩個(gè)盤、柜。兩盤、柜就位找正后,應(yīng)拉線測(cè)量?jī)杀P、柜間的水平和垂直距離,上下兩側(cè)都需測(cè)量,要緊貼盤、柜前后兩處的筋骨,不能帶側(cè)護(hù)板測(cè)量,防止誤差過(guò)大。兩柜間的誤差在5mm 以內(nèi),便于母線橋的安裝。其他盤、柜的就位安裝,方式同單列盤、柜的安裝。盤、柜的固定。共有兩種固定方式,應(yīng)根據(jù)不同要求施工。一種是盤、柜與基礎(chǔ)型鋼焊接固定,盤、柜至少有四處焊點(diǎn),盤內(nèi)側(cè)四角各焊一處,長(zhǎng)度20~40mm,焊口清理干凈,先刷防銹漆,干后再刷面漆。一般是按盤、柜種類不同,在基礎(chǔ)型鋼架上鉆孔攻絲,用螺栓固定盤柜。一般無(wú)特殊要求時(shí),低壓柜鉆準(zhǔn)12.2mm 孔,高壓柜鉆準(zhǔn)16.2mm 孔,分別用M12、M16 鍍鋅螺絲固定。
2.4 母線安裝
母線安裝時(shí),首先要事先對(duì)母線進(jìn)行檢驗(yàn),確保母線符合有關(guān)規(guī)定,具體而言,母線必須要保證光潔、平整,且不允許出現(xiàn)裂紋、沙眼等。母線穿接預(yù)拼要分清相序,按順序穿接。在母線穿接預(yù)拼完工以后就能夠開展柜內(nèi)組裝工序,必須要確保安裝過(guò)程嚴(yán)格依據(jù)規(guī)范進(jìn)行,且在安裝完工后還應(yīng)對(duì)其進(jìn)行驗(yàn)收。為了確保母線安裝工程的質(zhì)量,在安裝過(guò)程中要注意螺栓的平、彈墊,螺栓的力矩以及點(diǎn)紅等。
3.電纜敷設(shè)及接線管理
3.1 高壓電纜
高壓電纜的固定以及接線工作是低壓配電工程施工的重要環(huán)節(jié),必須高度重視。首先,在開展該項(xiàng)工作前要確保電纜實(shí)驗(yàn)結(jié)束并且合格,緊接著就是高壓電纜的固定以及接線工序。為了防止接線端子處承受電纜的拉力以及張力,要對(duì)高壓電纜進(jìn)行固定。具體的固定方法有多種,但是實(shí)際固定時(shí)要依據(jù)具體情況來(lái)定。例如,當(dāng)電纜在電纜溝中時(shí),可采取扁鋼制作的卡子來(lái)固定,此時(shí)還應(yīng)該墊外皮以保護(hù)電纜;當(dāng)電纜處于夾層中時(shí),則將電纜固定于走線架之上。固定工作完成之后即可進(jìn)行接線工作,接線主要是將電纜頭和接線端子連接,而且還應(yīng)該涂上導(dǎo)電膏,此外,還應(yīng)該注意接好電纜的接地線。
3.2 控制電纜
控制電纜的敷設(shè)是電纜敷設(shè)的要點(diǎn),這一工序開展前也要進(jìn)行必要的檢查工作,以確保敷設(shè)的電纜合格。在控制電纜的敷設(shè)過(guò)程中,要嚴(yán)格依據(jù)施工規(guī)范來(lái)進(jìn)行。
4.低壓配電工程質(zhì)量控制
4.1 設(shè)備施工階段的安全、質(zhì)量控制
設(shè)備的施工階段是整個(gè)低壓配電工程施工的重要環(huán)節(jié),其主要包括高低壓柜的就位、高低壓橋架的安裝,母線的安裝等多個(gè)步驟。在工程的質(zhì)量控制上必須要嚴(yán)格抓好這一環(huán)節(jié)的施工質(zhì)量,確保設(shè)備施工的安全、可靠。具體有以下幾點(diǎn):①設(shè)備安裝必須要依照規(guī)范進(jìn)行;②設(shè)備安裝時(shí),有關(guān)人員應(yīng)該結(jié)合以往工程經(jīng)驗(yàn),抓住施工質(zhì)量通病,重點(diǎn)進(jìn)行控制管理;③還應(yīng)對(duì)設(shè)備安裝階段的進(jìn)度進(jìn)行控制,以確保工程的正常開展。
4.2 設(shè)備調(diào)試階段的安全、質(zhì)量控制
設(shè)備調(diào)試階段是低壓配電工程施工的后續(xù)環(huán)節(jié),必須要予以重視,要嚴(yán)格依據(jù)調(diào)試方案進(jìn)行,保證調(diào)試過(guò)程的科學(xué)、合理。具體的調(diào)試工作主要包括以下幾點(diǎn):①對(duì)變壓器、封閉母線、真空斷路器、高壓電纜等進(jìn)行耐壓試驗(yàn);②變壓器要測(cè)量各繞組的直流電阻值;③高壓真空斷路器要做失壓脫扣試驗(yàn)和重合閘試驗(yàn);④高壓柜一段和二段聯(lián)絡(luò)試驗(yàn)等。
4.3 送電前準(zhǔn)備階段的安全、質(zhì)量控制
送電前的準(zhǔn)備階段工作內(nèi)容繁多,且均必不可少。具體的準(zhǔn)備工作有:計(jì)量表的安裝;負(fù)控裝置的安裝;進(jìn)線保護(hù)的整定;運(yùn)行規(guī)程的編制;運(yùn)行人員的培訓(xùn);變配電室安全用具的配備;完善配電房門的防小動(dòng)物設(shè)施;與高壓檢察員聯(lián)系組織供電分公司對(duì)施工進(jìn)行檢驗(yàn)等。
4.4 送電階段的安全質(zhì)量控制
送電階段可以說(shuō)是低壓配電工程投運(yùn)后的環(huán)節(jié)。這一環(huán)節(jié)的質(zhì)量直接關(guān)乎到人們的正常生產(chǎn)生活用電。送電階段的操作必須要嚴(yán)格按照規(guī)范要求執(zhí)行。